Denver Street Reconstruction Projects Impact Santa Fe Drive Small Businesses
The $29 million Santa Fe Streetscapes Project in Denver aims to improve safety and accessibility by reconstructing the roadway between West 6th and West 13th Avenues, cbsnews.com reported. While city officials state the voter-approved Vibrant Denver Bond Program initiative will widen sidewalks and upgrade utilities, local business owners report that ongoing construction, road closures, and communication gaps are significantly harming their sales.
Business Owners Report Revenue Drops and Communication Challenges
Sasha Zanabria, owner of El Taco de Mexico located at Santa Fe Drive and West 7th Avenue, reported a 30% drop in sales since construction began in August. Zanabria stated that confusing detours and a lack of direct notifications regarding street closures have complicated customer access. She noted that she discovered unexpected closures independently while attempting to direct traffic along West 7th Avenue with homemade signs. Swift’s Breakfast House and the Nail and Skin Studio also operate along the corridor, with operators noting that while the infrastructure upgrades are necessary, construction phases introduce severe commercial hurdles.
City Officials and Utility Crews Maintain Construction Schedules
Denver officials reported that the streetscape project remains on schedule, with multiple agencies coordinating the work to minimize disruptions. Denver Water initiated the replacement of 2,800 feet of aging water mains—some dating back 136 years—between West 7th and West 12th Avenues on August 10. Utility representatives confirmed that this phase was more than halfway complete by October 8 and remains on track to conclude by the end of 2026. Xcel Energy scheduled additional gas main replacements between West 6th and West 8th Avenues starting October 12, while stormwater improvements and roadway reconstruction between West 12th and West 13th Avenues are slated to begin later in October.
Calls for Financial Relief and Grant Programs
Affected business owners are pressing city leaders to establish financial assistance programs similar to those deployed during the East Colfax Avenue Bus Rapid Transit project, where the Denver Urban Renewal Authority issued approximately $1 million in Community STAND grants. City representatives emphasized that at least one lane of traffic remains open throughout construction, business access is maintained, and drivers are directed toward East 6th Avenue and northbound Speer Boulevard. Officials also confirmed that neighborhood events like the First Friday Art Walks will proceed as scheduled while utility and streetscape phases advance toward a final projected completion in 2028.
Frequently Asked Questions About the Santa Fe Streetscapes Project
When is the Santa Fe Streetscapes Project scheduled for completion?
The full project is scheduled to finish by the end of 2028, though utility replacement phases managed by Denver Water and Xcel Energy are slated to conclude by the end of 2026.
What specific utility upgrades are currently underway?
Denver Water is replacing more than 2,800 feet of 136-year-old water mains between West 7th and West 12th Avenues, while Xcel Energy is replacing gas mains between West 6th and West 8th Avenues.
What financial relief options are business owners requesting?
Business owners like Sasha Zanabria are asking for direct financial grants comparable to the $1 million in Community STAND grants issued by the Denver Urban Renewal Authority during the East Colfax Avenue project.