- Harwood voters rejected the measure 325 to 105 in the November 2026 election.
- Applied Digital is building the 1 GW Polaris Forge 2 campus outside Harwood.
- The company signed a 15-year, $5 billion deal for 200 MW with an unnamed investment-grade hyperscaler.
- Applied Digital announced a gigawatt-scale project in Finland with first power expected in 2028.
More than 40 anti-data-center measures appeared on local ballots across the United States during the 2026 midterms as a “blue wave” swept in Democratic candidates pledging to halt digital-infrastructure projects, Data Center Dynamics reported.
Harwood was the lone municipality to turn one down.
The proposed ordinance would have mandated independent environmental and infrastructure reviews plus public hearings for data centers and other large industrial developments. The 75.6 percent “no” vote represented 325 residents; 105 voted in favor.
Applied Digital’s local strategy
Applied Digital is the only data-center operator building in North Dakota. Its Polaris Forge 2 campus outside Harwood is designed for up to 1 GW of capacity. Last year the company disclosed a 15-year agreement to supply 200 MW to an undisclosed investment-grade hyperscaler, a contract valued at $5 billion, with an option for the same customer to take the remaining 800 MW when the campus comes online.
Wes Cummins told Data Center Dynamics before the election that the company has worked to “earn the right” to build in Harwood and elsewhere in the state. “Real estate is a very localized issue,” Cummins said. “We spend a lot of our time in the communities where we operate and trying to address any issues that come up.”
He added that being the sole data-center builder in North Dakota — rather than one of hundreds competing in Texas — has allowed the company to develop its reputation quietly.
“What we do in these communities earns us the right to do it again in another community,” Cummins said. “So if we do a good job, we’ll be welcomed in a new place. If you partner with the community in the right way, if you’re transparent and if you pay attention to the small details that people often overlook, you’ll do a good job and you’ll build a great reputation.”
Financial impact for Harwood
A company statement emailed to Data Center Dynamics after the vote highlighted a $100 million investment in local grid upgrades and $965,000 in grants to community organizations. Mayor Blake Hankey told The Washington Post the data center would generate $1.65 million in annual property-tax revenue — six times Harwood’s total 2024 revenue.
Cummins said he does not expect the broader anti-data-center sentiment to fade. “It’s not going away,” he said. “There’s a general consensus among members of both parties that they hate data centers, but I would say it’s a macro debate topic and data centers are becoming a scapegoat for a lot of other things. That probably won’t change, and it won’t make things easier in some places, but it does mean that places like where we are will continue to stand out.”
European expansion in Finland
Applied Digital also operates campuses in Alabama and Louisiana. In October the company announced a gigawatt-scale project at an undisclosed site in Finland, with initial power availability targeted for 2028.
Cummins said the first phase will provide 100 MW. “It’s paired with renewable energy and it’s in an area where a lot of other data centers are being built, so you have readily available infrastructure like fiber,” he told Data Center Dynamics. “This is the culmination of 18 months of site hunting in Europe to find the best one for us, and we now believe we’ve found it.”
The European push is part of a strategy Cummins describes as “catching six Pokémon” — a reference to six investment-grade hyperscale customers with deep balance sheets, according to Datacenterdynamics. “We’ve already caught three of the Pokémon, and I expect we’ll catch the other three,” he said.
“These customers, or potential customers, have been asking us more and more about what we have available in Europe, so we’ve formed a small European team and we expect that to grow.” Cloud AI company CoreWeave is one known U.S. customer; the others have not been disclosed.
The company’s scale is reflected in a portfolio of over 1.6 GW of total contracted critical IT load and 2.2 GW of grid-connected peak load. As of November 23, 2026, Applied Digital reported that its total contracted base-term lease revenue exceeds $41 billion.
Design flexibility for shifting AI workloads
The Finland campus will use the same design framework Applied Digital employs across its U.S. facilities, emphasizing flexibility for evolving AI density requirements. “We’ve designed our facilities with very large data halls relative to the amount of power we consume, because of the high power density,” Cummins said. “This can seem a little counterintuitive, because if you look at the chip roadmaps, it seems like power densities just keep going up. But I think there’s a possibility that at some point in the future, power densities go down. So we build a very wide form factor to be able to accommodate that, and if power densities go back to 10 kW per rack, we have the space to do that.”
The design includes 100 percent liquid-cooling coverage with 80 percent air-cooling availability. “The idea is to provide maximum flexibility for the future,” Cummins said. “Our customers often tell us they’ll need more air cooling in the future for certain types of inference deployments, so I think we’ll be happy with the design decisions we’ve made.”