Jacksonville, Florida, ordered Keystone Properties to stop accepting coal ash from a Puerto Rico power plant within five business days and to remove all stockpiled ash from its Talleyrand terminal on the St. Johns River within 45 calendar days, Mayor Donna Deegan announced Nov. 17.
The order, signed Nov. 16 by interim Administrative Services Director Al Ferraro, declares the ash a solid waste under Jacksonville’s ordinance code and says Keystone never obtained the required certificate that triggers a public hearing and City Council approval before such material can be received and stored. The five-day deadline to halt intake falls on Monday.
City orders Keystone to stop ash operations
Deegan said Keystone has for years accepted thousands of tons of ash “from a generating plant in Puerto Rico,” stored it on the riverbank and trucked it to the Chesser Island landfill in Georgia without submitting the operation for municipal review, according to Periodicolaperla. The order states that temporary storage “does not change the nature of the material” and that continued receipt and storage without authorization “represents a risk to public health, safety and welfare, and requires immediate correction.”
Citing the U.S. Environmental Protection Agency, Deegan warned that coal ash contains mercury, cadmium and arsenic and, without proper handling, can contaminate surface water, groundwater, drinking water and air. The city’s determination also rejects AES Puerto Rico’s characterization of the material — branded as Agremax — as a beneficial construction aggregate rather than a toxic waste.
Federal lawsuit triggered city enforcement action
Deegan acknowledged that a federal lawsuit filed in August by the environmental group St. Johns Riverkeeper brought the operation to the city’s attention. The suit alleges Keystone stored ash on unlined ground and that pollutants from the waste are reaching the St. Johns River and groundwater. U.S. District Judge Jordan E. Pratt set a schedule on Oct. 27: discovery ends in January 2028 and a bench trial is slated for October 2028.
In a court filing, Keystone denied all allegations, challenged Riverkeeper’s standing to sue and argued the Clean Water Act claim is improper because the company is negotiating a consent order with the Florida Department of Environmental Protection to “address and resolve” all site issues. The municipal order, however, rests on a separate violation: Keystone lacks the local certificate required by Jacksonville regardless of any state permits or negotiated agreements.
City mandates ash removal rules and fines
While removing the ash, Keystone must cover the piles before material leaves the site, control fugitive dust and prevent runoff or migration into the river. The company must report to the city every seven business days the tonnage removed, the transporter and the destination. Violations carry civil penalties of up to $2,000 per infraction, per day.
Pressure on AES Puerto Rico’s disposal timeline
Puerto Rico’s Act 40 of 2017, as amended by Act 5 of 2020, bans coal ash disposal on the island and sets a general 180-day limit for temporary storage. Extensions are granted only through Administrative Order 2021-16 from the Department of Natural and Environmental Resources, which allows a 30-day waiver — extendable only during a declared natural-disaster emergency — for causes such as natural disaster, force majeure, a governor’s emergency declaration or remediation of ash dumped on innocent third parties.
A municipal order blocking a private marine terminal is not listed among those causes.
The regulation defines force majeure as an “unforeseeable or inevitable” circumstance, but Keystone had already received a municipal citation in 2023, a state warning in May 2026 and the federal lawsuit in August — factors that may undermine a force-majeure argument.
Cost implications for Puerto Rico ratepayers
A third amendment to the AES–Puerto Rico Electric Power Authority contract shifts the cost of off-island ash handling, transport and disposal to PREPA customers — not the generator. AES estimated that bill at $222 million for 2019–2027. A change of port, route or landfill could increase those costs, La Perla del Sur reported.
The next dated event in the federal case is the close of discovery in January 2028.