Only 34 per cent of 1,448 health facilities earmarked for construction or renovation have been completed even though the central government has released Sh233 billion since 2025, Tanzania’s nutrition compact review heard in Dodoma on Monday.
Dr Rashid Mfaume, director of health services, social welfare and nutrition at the President’s Office – Regional Administration and Local Government (TAMISEMI), presented the figures at the 10th review of the nutrition compact’s implementation for 2025/26. Of the Sh233 billion granted, Sh141 billion had been spent but only 492 facilities were finished, he said.
“The problem is not money. The problem is completing the facilities,” Dr Mfaume said.
He told the meeting — attended by regional and district leaders, health officials and development partners, with Minister Riziki Shemdoe as guest of honour — that some councils had held construction funds for months or years without starting work.
He proposed seeking ministerial approval to reallocate money that remains unused for long periods to areas with more immediate needs, a proposal not yet adopted as policy. Dr Mfaume also urged councils to complete buildings in phases where necessary and to use their own revenues to finish facilities requiring relatively small additional amounts.
A parallel water and sanitation assessment showed only 45 per cent of facilities covered by a Sh20.17 billion programme had been completed.
On digital systems, Dr Mfaume reported that the government’s electronic health-facility management system, GOT-HoMIS, had been installed in 97 per cent of facilities assessed, but usage varied widely.
“We have praised you for installing it, but you are not using it. He added that tighter electronic payment controls had raised weekly collections from below Sh1 billion to Sh3.4 billion and urged facilities to stop receiving cash payments directly through service providers.”
Suitable buildings, electricity and installation arrangements were among the constraints discussed.
Local-government nutrition spending reached Sh70.8 billion against a Sh67.22 billion target for the period 2021 to 2025/26, the review heard. Those figures describe the 2022 survey, not a new measurement in 2026.
Tanzania’s nutrition compact review for 2025/26 convened in Dodoma on Monday because the city became the official capital in 1996 and hosts the President’s Office – Regional Administration and Local Government (TAMISEMI), whose director, Dr Rashid Mfaume, presented the implementation figures to regional and district leaders and development partners.
In 2023, the national government under President Samia Suluhu unveiled the new State House in Dodoma, marking the relocation of government duties to the city, while Dar es Salaam has remained the commercial and maritime capital retaining the state house Ikulu and a number of government functions.
UNICEF highlighted that undernutrition costs Tanzania 2.7 per cent of GDP, with effective interventions generating seven shillings in economic benefits for every shilling invested.