The U.S. Army Corps of Engineers (USACE) has released a draft report recommending a $1.5 billion coastal flood protection plan for Boston, featuring 20 distinct infrastructure projects. The proposal, known as the Boston Coastal Storm Risk Management study, aims to safeguard neighborhoods including East Boston, Charlestown, downtown, South Boston, and Dorchester from rising sea levels and storm surges through 2075.
The Proposed Coastal Infrastructure Strategy
The USACE proposal focuses on a combination of structural and non-structural measures to mitigate flood risks. According to the official draft report, the strategy prioritizes the construction of floodwalls, levees, and deployable flood barriers at critical points along the city’s waterfront.
These projects are designed to protect against a "1% annual chance event"—a storm surge with a 1-in-100 probability of occurring in any given year. The plan specifically targets areas identified as high-risk due to low-lying topography and high concentrations of critical infrastructure. By installing these barriers, the Corps intends to reduce the economic impact of flooding on both public property and private real estate.
Geographic Scope and Project Locations
The study divides the city into several focus areas, each requiring tailored interventions. The 20 projects are distributed across the following neighborhoods:
- East Boston: Focused on protecting the waterfront from surge events that could impact residential areas and Logan International Airport access.
- Charlestown: Involves perimeter hardening along the Mystic River and Boston Harbor.
- Downtown and North End: Aims to protect the financial district and historical infrastructure from harbor-side flooding.
- South Boston and Dorchester: Prioritizes the protection of residential communities and the industrial waterfront, which are increasingly susceptible to high-tide flooding.
Project Funding and Future Implementation
The $1.5 billion estimate covers both construction and long-term maintenance costs. As a federal project, the implementation requires a partnership between the USACE and the City of Boston.

According to the City of Boston’s Climate Ready Boston initiative, the federal funding would typically cover 65% of the project costs, while the remaining 35% would be the responsibility of the non-federal sponsor—in this case, the city. The project is currently in the draft phase, meaning it is subject to public comment and final approval from the Office of the Assistant Secretary of the Army for Civil Works before funding is locked in.
Comparison of Flood Mitigation Approaches
The USACE plan differs from localized climate resilience efforts previously undertaken by the City of Boston. While the city has focused on neighborhood-scale projects like elevated parks and seawalls, the USACE proposal provides a more comprehensive, system-wide approach.
| Feature | City-Led Resilience Projects | USACE Coastal Risk Plan |
|---|---|---|
| Scope | Neighborhood-specific | City-wide, integrated network |
| Primary Goal | Localized adaptation | Storm surge/flood prevention |
| Funding Source | Municipal/State funds | Federal/Local cost-share (65/35) |
Path Toward Final Approval
The USACE is currently soliciting feedback from residents, environmental groups, and municipal stakeholders. Following the public comment period, the agency will review the input to refine the feasibility study. If the plan is approved, the project will move into the Pre-construction, Engineering, and Design (PED) phase. Officials have emphasized that this process is multi-year, and construction timelines will depend on congressional appropriations and local legislative support.
Keep reading