Arizona Attorney General Calls for Delay of Cochise County Vote on SpaceX Data Center

Arizona Attorney General Kris Mayes on Thursday asked Cochise County officials to delay a Dec. 9 vote on a proposed SpaceX data center, saying state and federal agencies need more time to review the project. Mayes sent a…

Side-by-side image: on the left, a draft site plan of a proposed SpaceX data center campus near the Willcox Playa in Cochise

Arizona Attorney General Kris Mayes on Thursday asked Cochise County officials to delay a Dec. 9 vote on a proposed SpaceX data center, saying state and federal agencies need more time to review the project.

Mayes sent a letter to the Cochise County Planning and Zoning Commission arguing the panel should wait until all approvals are in hand. The commission is scheduled to vote Dec. 9 on a special-use permit for the development, according to the county’s published agenda.

“The people of Cochise County deserve answers before county officials approve a project of this magnitude,” Mayes said in a statement accompanying the letter.

The facility, proposed by a SpaceX affiliate called Tombstone Resources LLC, would occupy roughly 747 acres along U.S. Highway 191 near the town of Cochise. Plans call for up to nine computing buildings with a total power draw of about 6 gigawatts — nearly 20% of Arizona’s total generation capacity, Mayes wrote. That load approaches 1.5 times the output of the Palo Verde nuclear plant west of Phoenix, the nation’s largest power producer, and could serve roughly 1 million Arizona homes, according to a utility estimate cited by KTAR.com.

KJZZ reported the project’s estimated cost at $50 billion and its size at 750 acres with a 6,000-megawatt demand. For comparison, Arizona Public Service recorded a system peak of 9,164 megawatts this year.

Mayes’ letter lists unresolved questions: where the campus would get most of its electricity, how much groundwater the power generation would consume in an area already short on water, and whether rural fire departments could respond to a blaze among thousands of large batteries.

She also cited traffic impacts, wildlife disruption, and proximity to military testing ranges.

The attorney general has called for a statewide pause on new data centers and said any permit for this project should not take effect until every state and federal approval is secured.

Mayes’ office will hold a town hall on Dec. 3 at 5:30 p.m. in the Cochise Elementary School gymnasium, ahead of the commission’s hearing.

SpaceX did not immediately respond to requests for comment from the outlets reporting this story.

What the project proposes

Tombstone Resources LLC, the SpaceX-linked entity behind the application, seeks a special-use permit for a “Data Center and BESS” — battery energy storage system — on agricultural land near the Cochise Stronghold area. County documents show the site plan includes nine buildings ranging from several hundred thousand square feet each, plus substations and water storage tanks.

The applicant’s narrative says the campus would support Starlink satellite operations and artificial-intelligence workloads, leveraging SpaceX’s vertical integration of launch, connectivity, and compute. MarketScreener notes SpaceX’s connectivity segment already operates roughly 9,600 Starlink satellites serving customers in more than 164 countries, according to Marketscreener.

Arizona Attorney General Kris Mayes listens to speakers at a town hall on Wednesday, Oct. 15, 2026
Photo: kjzz.org

Project would consume fifth of state power

The 6-gigawatt demand figure dominates the regulatory debate. Mayes wrote that the project would consume nearly one-fifth of Arizona’s total generating capacity, a claim that utility resource plans generally support. The Arizona Corporation Commission has open dockets on long-term resource adequacy, and several large data-center proposals are already in queue across the state.

Groundwater is the other flashpoint. The Willcox Basin, which underlies the project area, has been designated an Active Management Area candidate due to declining aquifer levels. Agricultural users and rural residents have reported dry wells in recent years. Mayes’ letter asks for a “comprehensive water-supply analysis” before any permit takes effect.

Rural fire districts lack battery training

Lithium-ion battery installations of this scale are relatively new to rural fire districts. The Sunsites-Pearce and Cochise Stronghold fire departments rely heavily on volunteers and have limited hazardous-materials training. Mayes asked whether mutual-aid agreements and specialized suppression systems are in place. The county’s emergency-management office has not published a formal risk assessment for the site.

Permit approval moves to county supervisors

The Planning and Zoning Commission’s Dec. 9 meeting remains on the calendar. If the commission approves the permit, the Cochise County Board of Supervisors would have final say. Mayes has not filed litigation but reserved the right to challenge any approval that precedes completed state and federal reviews.

FAQ

When is the Cochise County vote scheduled?

The Planning and Zoning Commission is set to vote Dec. 9 on the special-use permit for the SpaceX data center.

How much electricity would the campus use?

About 6 gigawatts, or roughly 20% of Arizona’s total generation capacity, according to Attorney General Kris Mayes.

Who is the applicant?

Tombstone Resources LLC, an entity linked to SpaceX, filed the application for the data center and battery storage campus.

Mayes, born in Prescott and a former editor of Arizona State University’s State Press, began her career as a political reporter for The Arizona Republic and later co-authored a book on the 2000 presidential campaigns.

She served on the Arizona Corporation Commission from 2003 to 2010, focusing on pipeline safety and renewable energy, before leaving the Republican Party in 2019. Elected attorney general in 2022 by a 280-vote margin after a recount, she became the second woman and the third openly lesbian woman elected to the office nationwide.

What happens after the Dec. 3 town hall?

The attorney general’s office will gather public input, but the commission’s Dec. 9 vote proceeds unless the panel itself votes to delay.