Brooklynites are pushing the city to abandon its $4 billion plan to rebuild the aging Brooklyn-Queens Expressway, arguing that the current proposal locks the borough into decades of outdated, car-centric infrastructure.
During a virtual public meeting held on Thursday night, residents and community advocates urged the Department of Transportation to shift its focus away from the highway’s existing truck-first model, Streetsblog New York City reported.
The agency is currently gathering feedback for a required environmental review of its BQE Central project, which aims to rehabilitate the deteriorating section of the highway between Atlantic Avenue and Sands Street.
According to the Oct. 2 draft scope of work, the DOT plans to study the impacts of building a temporary bypass—which includes a flyover above the Brooklyn Bridge’s approach in Dumbo—versus not rebuilding the structure at all.
And that’s not a choice for communities."
The project, which is scheduled to begin in 2030 and last for a decade, is intended to extend the BQE’s lifespan until 2080. DOT Commissioner Mike Flynn has maintained that the city must prioritize the renovation to support the 130,000 motorists—including 13,000 trucks—who use the route daily.
The agency asserts that it has run out of time to pursue larger overhauls, noting that nearly 90 percent of goods in New York City are moved by truck.
The proposed bypass has also drawn concern from residents of 360 Furman Street, where the temporary structure would sit within four feet of the building’s facade. "A decade is not temporary for the people who have to live next to it," said resident Diane Genova.
She suggested that the city consider alternative construction methods, such as a lane-by-lane rebuild paired with a traffic reduction plan, to avoid the disruption of an entirely new highway.
The DOT will continue to draft an environmental impact statement over the coming year, with a final version expected in 2028. Following that, the city plans to initiate the Uniform Land Use Review Procedure (ULURP), which will require sign-offs from the City Council and state officials to alienate parkland for construction.
He added that the agency’s current plan does not prevent future efforts to rethink the highway, most of which remains under state control.
The agency is accepting public input through Jan. 11. Residents can submit comments via this contact form, by emailing BQECentral@dot.nyc.gov, or by mailing the Department of Transportation’s Division of Bridges.