- Rail projects worth over €350 million were terminated after a review found they were not securely funded.
- Budget for 2027 set at nearly €628 million, focused on accelerating and completing started projects.
- 23 new Alstom trains are due next year, funded by EU regional and climate programs.
Transport Minister Georgi Peev said the ministry cancelled procedures for unfinished rail projects valued at more than 350 million euros because financing was not secured.
“The most expensive project is the unfinished one. The 2027 budget allocates nearly 628 million euros from the national budget, an increase on almost every major line compared with 2026, Утро Русе reported, according to Mediapool. Peev described it as conservative and pragmatic, with the priority on accelerating and finishing started projects while preparing the investment program for the EU’s 2028–2034 financial framework. Peev cited the modernization of the Vidin-Sratsimir railway line, part of the Vidin-Sofia route, as an example of a terminated project with an indicative value of nearly 300 million euros and double that of the corresponding section on Romanian territory, for which financing had not been secured.”
New Trains Repair Existing Rolling Stock
Twenty-three new Alstom trains are expected to arrive in 2027, financed through the EU’s Regional Development Program and the Social Climate Plan, Peev said. At the same time, 33 million euros in capital transfers are earmarked for repairing BDZ’s existing rolling stock. In an August interview with Еconomic.bg, Peev said only 42% of BDZ passenger wagons are fit for service and repairs average 300 days against a normative 90 days, citing shortages of spare parts and qualified staff.
The 2027–2029 investment program for BDZ includes six positions totalling 99.3 million euros, among them six electric shunting locomotives for partially electrified depots at a cost of 24 million euros over three years, with 2.4 million euros in 2027, Еconomic.bg reported. The government has purchased a total of 60 new trains from Škoda and Alstom with European funds, most of which are already in Bulgaria.
Bulgaria North Macedonia Sign Corridor Tunnel Protocol
Bulgaria and North Macedonia will sign a protocol on Dec. 4 for a joint tunnel on Corridor 8, with Bulgaria leading the procurement and construction management, Peev said. DarikNews.bg reported the document will then go to the National Assembly for ratification. After years of delays, Corridor No. 8 is again in focus, with new projects from National Railway Infrastructure Company (NRIC) also directed towards it, Peev said.
Separately, design work will begin in 2027 for a completely new rail link from the Turkish border through Elhovo and Yambol, intended as a key alternative to the Bosphorus on the Middle Corridor.
“To be successful and meet these expectations, we are doubling the Plovdiv–Svilengrad line, but that will not be enough. For this reason we will design an entirely new rail connection from the Turkish border through Elhovo and Yambol to be included in the TEN-T network,” Peev said, mediapool.bg reported.
Georgi Peev has served as the Minister of Transport and Communications since his appointment to the Cabinet, bringing over 20 years of expertise in civil aviation, strategic management, and international cooperation. Prior to this role, Peev began his career at BULATSA in 2002 as an air traffic controller, progressing through positions including instructor and head of department before becoming Director of the Air Traffic Control Directorate.