Heavy flooding in late October and early November severed the 64-mile Cumbres & Toltec Scenic Railroad in two places between Cumbres Pass, Colorado, and Chama, New Mexico, with preliminary track and roadbed repair estimates reaching $5 million, the railroad and the Alamosa Citizen reported.
Two washouts cut the line
The first storm on Oct. 23 eroded part of the eastern approach to the Chama River bridge at milepost 343.5 in New Mexico.
Near the top of Cumbres Pass at Coxo, milepost 331.5 in Colorado, the Nov. 1 flood carried away an entire fill approximately 100 feet long, 100 feet wide and 80 feet deep, washing away the adjoining hillside, coyotegulch.blog reported. Rebuilding it will require about 15,000 cubic yards of material, new culverts and extensive hillside stabilization before trains can pass, railway.supply reported.
Engineers inspected the railroad’s bridges, including the Chama River bridge, and found no structural problems with the spans themselves, the railroad said in its own statement carried by lok-report.de.
Station and water-supply damage add to the bill
Floods severed the historic Cumbres & Toltec Railroad in two places, with repairs estimated at $5 million.
Station damage may add as much as $1 million to the total, railway.supply reported.
The Chama water supply is a separate problem. Both the system serving the shop and the tank used to fill steam locomotive tenders suffered extensive damage, railway.supply reported.
The railroad shops and the steam locomotives inside them for annual inspections and repairs were not damaged, railway.supply reported.

Holiday trains will run on revised routes
“Santa’s Holiday Express” trains will operate as scheduled on Dec. 5 and 6 from Chama and on Dec. 12 and 13 from Antonito, using a modified route through the historic station and surrounding grounds, the railroad said, according to lok-report.de. The railroad will also enter a decorated festival car in the “Parade of Lights” in Chama on Dec. 5 at 7:30 p.m. and in Antonito on Dec. 12 at 7:00 p.m., lok-report.de reported.
The 2026 regular operating season had already concluded, KOB reported. The railroad aims to welcome passengers for the 2027 season starting Memorial Day weekend, May 29, the railroad said, according to lok-report.de.
Worst damage since 1970, commissioner says
“The combined damage from both floods was the most significant that we’ve experienced since the railroad was bought from the Denver Rio Grande Western in 1970,” said Ken Bitten, a member of the Cumbres & Toltec Scenic Railroad Commission, in a telephone interview, coyotegulch.blog reported, according to Lok Report.
“The families, particularly in Chama, were devastated personally. Houses flooded. The whole devastation in Southwest Colorado didn’t spare trauma,” Bitten said. “Fortunately, we didn’t have anything as severe in Antonito, but on the west end of the railroad, the families and employees that live there are dealing with their own personal crises.”
“That also means that there is, and I’ll characterize this as relentless determination to ensure that we’re going to get over this, we’re going to get through it, we’re going to find a way, and we’re going to keep railroading,” Bitten told coyotegulch.blog.

Chama yard and depot suffer water and mud damage
Floodwater surged into the Chama rail yard and crossed an adjacent RV park, producing isolated washouts along the tracks, the railroad’s damage assessment published by the Alamosa Citizen showed. Several inches of water and mud entered parts of the 1899 depot building, damaging floors and lower walls and forcing cleanup and repair work, lok‑report.de reported.
The historic coal tipple, sand‑drying house and delivery tower were also hit, railway.supply reported. Station damage may add as much as $1 million to the overall cost, the same assessment indicated.
Water‑supply system for steam locomotives heavily damaged
Steam locomotives cannot operate without that supply, the assessment stressed. The commission must coordinate with the New Mexico State Engineer on repairing or replacing the inlet structure and headgate, and a cost estimate will follow only after the state approves the plans, railway.supply reported.