The Waalse Gewest has ordered Google to halt construction of a datacenter in the municipality of Aiseau-Presles after an inspection found the tech giant was continuing work despite an ingested permit.
The order was issued on Thursday, 26 November 2026, following an inspection initiated by Waalse minister of Spatial Planning François Desquesnes (Les Engagés) after Greenpeace accused Google of violating regulations, according to HLN.
According to Raphaël Stokys, an official for the Waalse Gewest, approximately 300 employees were present at the construction site during the inspection. Google, through its subsidiary Crystal Computing, had its permit for the project withdrawn after a change to its plans was rejected.
The company initially sought permission to build three datacenters and later requested to combine two of them into a single structure. It also sought to cool the facility using water from the Samber river instead of an air-cooling system, a change that led to the permit’s withdrawal after an appeal was filed. A hearing on the permits is scheduled for 7 January 2027.
The dispute began in August 2026 when Crystal Computing’s application for the modified project was denied. Minister Desquesnes vetoed the change, citing the use of river water for cooling as the reason for revoking the permit.
Despite this, Google proceeded with construction, a fact corroborated by satellite images reviewed by Greenpeace and the Belgian broadcaster VRT. The images showed continued building activity between 31 October and 13 November, including the completion of part of a roof and a wall.
In response to the halt order, Google stated its commitment to an “open and collaboration-oriented dialogue with the regional government and experts regarding the investments in Wallonia.” The company had already appealed the permit revocation to the Council of State in mid-October.
It remains unclear whether the current construction adheres to the original air-cooled plans or the rejected water-cooled version, though sources note that a company may continue building if it adheres to its original, approved permit.
How it unfolded
The dispute stems from an original permit Google received for a datacenter in Farciennes, Wallonië. The company initially applied to build three datacenters. Later, Google requested a modification to combine two of the planned structures into one and to switch from an air-cooling system to a water-cooling system using water from the nearby Samber river.
In a first instance, this modification was approved. However, after an appeal was filed by a citizen, Waalse minister François Desquesnes (Les Engagés) vetoed the change. According to RTBF, the minister said that the use of river water for cooling was not permitted, leading to the withdrawal of the renewed permit. In mid-October, Google’s subsidiary Crystal Computing appealed the revocation to the Council of State.
Where it stands now
Despite the permit being revoked and the appeal process ongoing, Google continued construction. Satellite images and footage from residents, reviewed by VRT, showed that work on the datacenter progressed between 31 October and 13 November. These images, as reported by the Belgian omroep VRT, showed that a section of the roof and a wall were further constructed during that period.
Greenpeace accused Google of proceeding with construction without a valid permit. The environmental organization said that Google was continuing to build the datacenter in Aiseau-Presles despite the permit being ingetrokken. In a reaction, the Waalse Gewest announced controls on the Google site to check whether ongoing work complied with the company’s permits.
The Waalse Gewest, or Walloon Region, is one of Belgium’s three federal regions and holds authority over environmental and spatial planning matters. The regional government, represented by officials like Raphaël Stokys, conducted the inspection to verify compliance, leveraging its regulatory power to enforce the construction stop.
During the inspection on 26 November, it was confirmed that the construction stop was not being respected. The Waalse Gewest then ordered the construction to be halted. “Google staat open voor een open en samenwerkingsgerichte dialoog met de regionale regering en de deskundigen”, a Google spokesperson stated.
The tech giant reiterated its commitment to dialogue, saying it is dedicated to an “open and samenwerkingsgerichte dialoog met de regionale regering en de deskundigen voor de investeringen in Wallonië”.