Irish Rail will run a temporary timetable on the Dublin–Maynooth line from Monday after a defect in the web plate of a bridge at Drumcondra forced speed limits and single‑train crossings that have disrupted punctuality.
Which bridge is affected and what was found?
Engineers identified a defect in the web plate of the central girder of bridge UBO13 on St Patrick’s Road at the western end of Drumcondra station during a planned inspection on 13 November, RTÉ reported.
What immediate restrictions were imposed?
Speed limits and a one‑train‑at‑a‑time rule were applied immediately, and the line was closed over the weekend of 14–15 November for remedial works and further investigation, the Irish Mirror reported from an Irish Rail statement.

How will the temporary timetable change peak services?
From 30 November until February or March 2027, 14 peak services will bypass Drumcondra — either diverting to or from Docklands station or rerouting via Newcomen junction between Broombridge and Connolly, Dublin People reported. The affected departures are:
- 06:29 Maynooth → Connolly (diverted to Docklands)
- 07:25 Connolly → Maynooth (starts from Docklands)
- 07:59 Grand Canal Dock → Maynooth (via Newcomen)
- 08:15 Maynooth → Pearse (via Newcomen)
- 08:23 Pearse → Maynooth (via Newcomen)
- 16:00 Pearse → Maynooth (via Newcomen)
- 16:12 Pearse → Maynooth (via Newcomen)
- 16:39 Grand Canal Dock → Maynooth (via Newcomen)
- 17:10 Maynooth → Connolly (diverted to Docklands)
- 17:29 Bray → Maynooth (via Newcomen)
- 17:39 Grand Canal Dock → Maynooth (via Newcomen)
- 17:51 Maynooth → Connolly (diverted to Docklands)
- 18:00 Connolly → Maynooth (starts from Docklands)
- 18:45 Connolly → Maynooth (starts from Docklands)
All other Maynooth line services remain unchanged, though minor delays may persist, Irish Rail said.
What happens to the Santa Special trains?
Railway Preservation Society of Ireland Santa Specials scheduled for the next three weekends will run between Dublin Heuston and Kildare instead of between Connolly and Maynooth, Dublin People reported.
Engineers identify bridge defect
Iarnród Éireann confirmed the defect was substantial enough to require a full bridge replacement, stating that while trains can continue to operate safely under restrictions, the deterioration identified means replacement is necessary.
Santa trains reroute due to defect
Iarnród Éireann has advised all customers using the line to expect temporary timetable changes from Monday 30 November onwards to manage the disruption safely.
Irish Rail operates all internal InterCity, Commuter, and DART railway services across the Republic of Ireland, with its network managed from Connolly and Heuston stations. In 2025, the organization carried a record peak of 55 million passengers, underscoring its extensive role in the country’s transportation system. Additionally, it jointly runs the Enterprise service between Dublin and Belfast with Northern Ireland Railways, further demonstrating its operational reach.
When will the bridge be replaced?
Irish Rail intends to replace the bridge over the St Brigid’s Bank Holiday weekend, 30 January to 1 February 2027, or sooner if possible, the Irish Mirror and Dublin People both reported from the same Irish Rail statement.