Motorists face an overnight closure of the Louis-Hippolyte-La Fontaine tunnel as restoration work progresses toward a four-lane configuration in December 2026.

Louis-Hippolyte-La Fontaine Tunnel Progresses Toward Four Lanes in December 2026

Motorists face an overnight closure of the Louis-Hippolyte-La Fontaine tunnel as restoration work progresses toward a four-lane configuration in December 2026.

  • The ministry scheduled full overnight closures on the A-25 in both directions.
  • Traffic shifts to the second renovated tube starting November 30.
  • A second lane toward the South Shore reopens on December 14.
  • Total project costs have reached 2,8 billion dollars, while public funds support the major infrastructure overhaul.

Overnight Closures Target A-25 and Tunnel for Upgrades

The ministère des Transports et de la Mobilité durable closed the A-25 and the tunnel overnight from November 20 to 21 for electrical and communication upgrades. Crews also tackled pavement work on the highway during that window.

Additional closures will occur between November 27 and December 14. These interruptions let workers reconfigure approaches and install new detection fiber and radiant cables damaged in previous incidents, according to the agency. Between November 18 and 23, various operations also required nighttime closures on Curatteau Street, on eastbound Souligny Avenue, and on westbound Highway 20 in the Sainte-Julie sector.

The complete weekend closure of the A-25 in the direction of Montreal starts on the weekend of November 27, while nighttime closures are scheduled heading toward the South Shore. During these operations, eastbound Souligny Avenue between Dickson and Honoré-Beaugrand streets closes 30 minutes prior to the complete shutdown of Highway 25, alongside access ramps leading from eastbound Souligny Avenue to northbound and southbound Highway 25.

Louis-Hippolyte-La Fontaine Tunnel Progresses Toward Four Lanes in December 2026
Photo: Gouvernement du Québec

Phased Reopening Schedule

Drivers will regain partial access at the end of November. On November 30, both Montreal-bound lanes move into the newly renovated second tube.

Two weeks later, on December 14, a second lane reopens toward the South Shore. This milestone restores two lanes of traffic in each direction. Starting December 14, a second lane toward the South Shore becomes available, and the ministry advises users to remain vigilant because the new lane configurations require an adaptation period.

“The opening of the second renovated tube and the return of a second lane toward the South Shore constitute a major and highly anticipated step for the project,” said Nicolas Girard, Minister of Transport and Sustainable Mobility.

Louis-Hippolyte-La Fontaine Tunnel Progresses Toward Four Lanes in December 2026
Photo: Lapresse

Project Scope and History

Before construction began, an average of 120 000 vehicles used the 1,5-kilometer sub-fluvial link daily, with trucks making up 13 % of that traffic. The infrastructure opened in 1967, and the current initiative marks its first major overhaul.

Since October 2022, approximately 350 construction workers have operated on site around the clock. Crews modernized electrical systems, upgraded ventilation, and improved fire protection while rebuilding A-25 pavement slabs.

Initially, the three-lane configuration consisting of two lanes toward Montreal and one toward the South Shore was supposed to stay in place until November 2025. The initial timeline had targeted a complete project finish by November 2024, but it was postponed several times for an extra duration of nearly three years.

Six-Lane Completion Set for Summer 2027 After Median Work

Full completion with all six lanes operating is scheduled for the summer of 2027, following median reconstruction and landscaping work. Finishing touches and landscaping operations will continue until the end of autumn 2027. The reconstruction of the Highway 25 central median on both sides of the tunnel will begin in the spring.