International Edition
Latest News
Business

Wallonia Halts Google Data Center Construction in Farciennes Over Permit Dispute

Wallonia ordered construction halted on Google's data center campus in Farciennes on Thursday after a modified permit for water cooling from the Sambre River was annulled in August, even as the company insists its original 2024 permit remains…

Wallonia Halts Google Data Center Construction in Farciennes Over Permit Dispute

Wallonia ordered construction halted on Google’s data center campus in Farciennes on Thursday after a modified permit for water cooling from the Sambre River was annulled in August, even as the company insists its original 2024 permit remains valid.

The stop-work order followed a Greenpeace urgent procedure filed Wednesday alleging that Google’s European subsidiary, Crystal Computing, was building beyond the scope of the original air-cooled design. Regional inspectors found about 300 workers on site Thursday, said Raphaël Stokys, a Walloon Region official.

Google obtained a 2024 permit for three smaller, air-cooled data centers on a 53-hectare site — roughly 74 soccer fields — at the Ecopôle business park spanning Farciennes, Aiseau-Presles and Sambreville. In 2025, Crystal Computing applied to merge two of the three buildings into one larger facility and switch from air cooling to water cooling, drawing up to 600,000 liters per hour from the Sambre, ITdaily reported.

In August, Desquesnes annulled the modified permit, arguing climate change could no longer guarantee sufficient water in the river for the proposed withdrawal. Google appealed to the Council of State, which is scheduled to hear the case on Jan. 7, 2027.

"The work carried out since the annulment decision was mainly aimed at preserving the site and guaranteeing its safety and security during the appeal procedure, and at continuing work allowed under the original permit, which is not contested and remains in force," Google said in its statement.

Greenpeace connected the Farciennes project to Google’s existing data center in Saint-Ghislain, near Bergen, where the organization says the company pumps a massive amount of water annually for cooling and returns only a quarter. The Saint-Ghislain campus, Google’s first outside the U.S., has grown to 90 hectares — about 126 soccer fields — since construction began in 2007, Humo reported.

"For one AI video, five liters of water must be pumped from the Sambre," said Melchior, a 40-year-old math teacher living near the Farciennes site, describing his realization of the water intensity of generative AI queries. Humo reported the figure based on the permit application’s hourly withdrawal rate.

Walloon officials are verifying whether current construction aligns with the original 2024 air-cooled permit. Greenpeace’s urgent procedure and the Council of State appeal are both ongoing.

"Regarding construction work permitted under that original permit, we will consult with the relevant authorities to determine our next steps," Google said.

The company has invested more than €11 billion in Belgium since 2007, it said in a recent statement. It announced an additional €1 billion investment when construction started at the Farciennes site in 2021.

About the author: Business Desk

Business Desk at Archynewsy.