Google Halt Data Center Work Over Water Dispute

The climate crisis is only going to intensify in our regions, said Nadia Cornejo, Greenpeace Belgique.

Google Halt Data Center Work Over Water Dispute

“The climate crisis is only going to intensify in our regions,” said Nadia Cornejo, Greenpeace Belgique. The Wallonian government has ordered the halt of Google’s data center construction at Aiseau-Presles.

The order, issued Thursday by the region’s delegated official Raphaël Stokys, comes after Google persisted with work on the 53-hectare site despite a permit refusal from August. On the day of the halt, approximately 300 workers were on site, according to Stokys.

Earlier in the week, the environmental organization had highlighted that 1,200 workers had been employed on the site for months. The Greenpeace complaint was triggered by citizens who observed the ongoing construction. The NGO sent a letter to the Walloon administration on Monday demanding the immediate stop to the work, citing the permit cancellation.

The dispute stems from a change to a project initially approved in 2024. Google’s subsidiary, Crystal Computing, had first planned to build three smaller data centers. In 2025, it modified its application to merge two into a single, larger facility and switched from air-based to water-based cooling, drawing water from the Sambre river.

Google Halt Data Center Work Over Water Dispute
Photo: L'Avenir

This revised permit was approved by the Walloon administration in April but faced a citizen-led legal challenge a month later. In August, during a historic drought in Belgium, Minister of Territory, Infrastructure and Local Government François Desquesnes annulled the modified permit. The decision cited the project’s significant water consumption, according to Lalibre.

Greenpeace contends that the water consumption would be immense. The organization points to a similar Google data center in Saint-Ghislain, which it says uses 1 billion liters of water annually for cooling. The NGO notes that only a quarter of this water is returned, with the rest lost to evaporation.

Google challenged the minister’s decision in the Council of State. An audience is scheduled for January 7. On October 17, the tech company filed a case for annulment and suspension with the Council of State against Minister Desquesnes. On November 16, several citizens and Greenpeace launched an application to intervene in the procedure, allowing them to argue their case.

Last week, the executive, led by Adrien Dolimont, established a new framework for data center developments. The new rules emphasize that projects must respect regional needs, align with industrial decarbonization goals, and not harm other economic activities.

Google Halt Data Center Work Over Water Dispute
Photo: Moustique

Greenpeace maintains that Google continued construction after the permit was revoked, a claim supported by satellite imagery, according to RTBF. The multinational’s actions have drawn criticism.

“For Google to continue building after its permit has been annulled gives an idea of the respect the multinational has for our regulations, our resources, the impact on our territories and our citizens”, Cornejo said.

In a statement, Google said it is committed to “maintaining an open and collaborative dialogue with the regional government and experts concerning our investments in Wallonia”.