Waterford Airport Runway Reaches 70% Completion Milestone
Waterford Airport’s runway development project has reached 70 percent completion, with construction advancing significantly between May and September. The milestone brings the South East facility closer to restoring scheduled commercial passenger services that have been offline since 2016.
Private Investment Funds 30 Million Euro Redevelopment
The redevelopment is being funded through a 30 million euro private investment. Workers turned the first sod on the site in May. Four months later, the physical layout of the expanded strip is clearly visible. Crews are extending the runway to 2,287 metres and widening it to 45 metres. These dimensions will allow larger commercial aircraft to operate from the airport.
Airlines Discuss Future Commercial Services
William Bolster has confirmed that discussions are currently underway with airlines regarding providing a service. The airport shared photographs on social media highlighting the site’s rapid transformation. Management thanked those involved in the project for their continued efforts and asked the public to speculate on how much further the site will advance by the festive season.
Frequently Asked Questions About the Runway Project
When did construction on the Waterford Airport runway begin?
Work on the site officially commenced in May with the turning of the first sod, and the project reached 70 percent completion by September.
Why was the runway expansion necessary?
The 30 million euro private investment aims to secure the long-term future of the airport and bring back scheduled commercial passenger flights, which have been absent since 2016.
What are the new dimensions of the runway?
The upgraded runway will measure 2,287 metres in length and 45 metres in width to accommodate larger commercial aircraft.