Major Blackout Hits Parts of Sumatra, Indonesia – News En.tempo.co

0 comments

Sumatra Electricity System Restored Following Major Grid Disruption

The electrical grid across Sumatra has returned to normal operations following a significant system disruption that impacted millions of customers. State electricity company PT PLN confirmed that full power was restored to the southern Sumatra, Jambi, and Bengkulu regions by early morning on Thursday, June 6, 2024.

Understanding the Scope of the Disruption

The technical failure, which began on Tuesday, June 4, 2024, at 11:00 AM, caused widespread instability across the island’s interconnection network. The outage originated from a disruption in the 275 kV Lubuk Linggau-Lahat extra-high voltage (EHV) air transmission line, a critical component of the Sumatra power grid. Because this line serves as a backbone for the regional interconnection, the failure triggered a cascading effect that impacted no less than 29,000 distribution substations.

According to Iwan Arissetyadhi, the Communication Manager and TJSL of PLN’s Distribution Main Unit for South Sumatra, Jambi, and Bengkulu (UID S2JB), the scale of the recovery operation was immense. Hundreds of field officers were deployed to manually normalize 458 medium voltage substations, which in turn brought power back to approximately 4.3 million customers across the affected provinces.

The Path to Recovery

Restoration efforts were methodical, prioritizing the safety and quality of the technical teams working in the field. By the time the final load from Bengkulu was reintegrated into the system at 1:02 AM on Thursday, the utility was able to confirm that the electrical system in South Sumatra and the Bangka Belitung regions had been restored to 100 percent capacity by 1:16 AM.

The Path to Recovery
Lubuk Linggau

PLN officials have emphasized that the company is currently conducting a thorough evaluation of the incident. This assessment is intended to identify the root cause of the transmission failure and implement necessary infrastructure improvements to prevent similar disruptions from affecting the Sumatra interconnection network in the future.

Key Takeaways

  • Event Timeline: The disruption began on June 4, 2024, and was fully resolved by June 6, 2024.
  • Primary Cause: Technical issues within the 275 kV Lubuk Linggau-Lahat extra-high voltage transmission line.
  • Impact: Approximately 29,000 distribution substations and 4.3 million customers in South Sumatra, Jambi, and Bengkulu were affected.
  • Current Status: The electrical grid is operating at full capacity, with an internal evaluation by PLN underway to enhance grid resilience.

Frequently Asked Questions

Why did the outage affect such a large area?

The Sumatra electrical grid relies on an interconnection network. When a critical high-voltage transmission line—such as the 275 kV Lubuk Linggau-Lahat line—experiences a failure, the resulting instability can trigger protective shutdowns across the interconnected system to prevent permanent damage to equipment.

[FULL] Breaking News! PLN President Director Apologizes Following Sumatra Blackout, Here Is the C…

Is the power grid in Sumatra stable now?

Yes, PT PLN confirmed that the system returned to 100 percent normal operations as of 1:16 AM on June 6, 2024. The utility is currently working on evaluations to ensure the long-term reliability of the transmission network.

What is being done to prevent future blackouts?

PLN is performing a comprehensive evaluation of the transmission network to identify vulnerabilities. The goal of this review is to implement technical safeguards that mitigate the risk of similar cascading failures across the Sumatra interconnection grid.

Related Posts

Leave a Comment